Construction for Electrical Substation & Far, OPF Building with Watch Tower, Guard House-1 of Water Intake Station for EPCC Project Oil Train 3, 4 And 5 In Garraf Oilfield.
PROJECT DESCRIPTION
Company(Client):
CPECC
ATCO Role:
Main Contractor
Total Project Value (USD):
379,180
Type Of Work:
Civil
Start Date:
July 2019
Completion Date:
Under Construction
Estimated Man-hours Consumed:
Estimated 12,600
Description:

Construction for Electrical Substation & Far, OPF Building with Watch Tower, Guard House-1 of Water Intake Station for EPCC Project Oil Train 3, 4 And 5 In Garraf Oilfield.



Al Dewaniyah Substation IDP Stage 2
PROJECT DESCRIPTION
Company(Client):
G.E Grid Solution
ATCO Role:
Main Contractor
Total Project Value (USD):
8,602,969
Type Of Work:
Civil
Start Date:
June 2019
Completion Date:
Under Construction
Estimated Man-hours Consumed:
287,000
Description:


Iraq Four 400KV/132KV Substation
PROJECT DESCRIPTION
Company(Client):
ELSEWEDY
ATCO Role:
Sub Contractor (JV with Al-Rawabi)
Total Project Value (USD):
9,778,231
Type Of Work:
Civil / Electrical / Mechanical
Start Date:
June 20199
Completion Date:
Under Construction
Estimated Man-hours Consumed:
Estimated 326,000
Description:


Provision of Engineering, Procurement, Construction and Commissioning (EPCC) of Oil Gathering Facilities Phase 4 For Petronas Carigali Iraq Holding B.V. Garraf Operation
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq Holding B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
68,397,508
Type Of Work:
Engineering, Procurement, Construction and Commissioning (EPCC)
Start Date:
October 2018
Completion Date:
Under Construction
Estimated Man-hours Consumed:
30,000 Engineering Mhr and 700,000 Site Mhr
Description:

- Tie-in for 24 Wellheads
- New development and Tie-in for 25 Wellheads
- Piping estimated dia inch 37000
- API 5L Pipe line 24” 4.8 km and 18” 2.2 km
- HDD for 24 Pipeline 01 nos
- 02 Substation and 02 Control Room Buildings
- 02 Substation and 02 Control Room Buildings
- Installation of MPFM s, WHCP,s Closed Drain Drums
- Installation of HIPSP, Honeywell Control System, UPS, FOC, Switchgears



Mechanical Works of EPCC Project of Oil Gathering Facilities Phase 3 For Petronas Carigali Iraq Holding B.V.’s, Garraf Operations
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq Holding B.V
ATCO Role:
Sub-Contractor
Total Project Value (USD):
5,081,304
Type Of Work:
Mechanical
Start Date:
April 2018
Completion Date:
Under Construction
Estimated Man-hours Consumed:
169,400
Description:

Pipe, Cathodic Steel Structure, Painting and Coating, Mechanical, Fire Fighting and HVAC Works & Installation of EPCC Project of Oil Gathering Facilities Phase 3 for PCIHBV
- Fabrication and laying of Pipeline 18” API5L grade 2500 M Hot/Cold induction bends 24 nos.
- Laying of FOC 5500 M



Civil Works of EPCC Project of Oil Gathering Facilities Phase 3 For Petronas Carigali Iraq Holding B.V.’s, Garraf Operations
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq Holding B.V
ATCO Role:
Sub-Contractor
Total Project Value (USD):
9,132,202
Type Of Work:
Civil
Start Date:
January 2018
Completion Date:
January 2019
Estimated Man-hours Consumed:
304,000
Description:

- Asphalt Road 55,000 sq M
- Buildings 3000 sq M
- RCC Foundation 7500 cu M
- Pipeline ROW preparation 63,000 cu M
- Pipeline Crossings Open Cut 03 nos



Provision of Engineering, Procurement, Construction and Commissioning (EPCC) of Garraf Central Control Building (GCCB) for Petronas Carigali Iraq Holding B.V.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq Holding B.V
ATCO Role:
Main Contractor
Total Project Value (USD):
10,587,432
Type Of Work:
Engineering, Procurement, Construction and Commissioning (EPCC)
Start Date:
August 2017
Completion Date:
March 2019
Estimated Man-hours Consumed:
630,000
Description:

Total Plot Plan Area= 14,000 sq. m, Total covered area for building=3,552 sq. m, Total Landscaping area=5,000 sq. m, Fence & Road around the building = 500m, Storm water drainage 300m, Covered Car parking 25 nos.
Honeywell DCS/SIS/FGS System (including 600 graphics, 165 I/O, 3 nos. Orion Consoles, 10 cabinets), ACS, PAGA, CCTV, VHF, Weather monitoring system and FOC.
Electrical works including Substation, Switchgear, Transformer 1.6KVA, EGD 425 KVA, UPS & Accessories.
Fire Detection & Alarm System, HVAC Package 150 tons.



Provision of Fabrication, Installation, Execution and Commissioning of Well Tie-Ins and Other Construction Services for Petronas Carigali Iraq Holding B.V
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq Holding B.V
ATCO Role:
Main Contractor
Total Project Value (USD):
7,505,610
Type Of Work:
Fabrication, Installation, Execution and Commissioning
Start Date:
March 2017
Completion Date:
Under Construction
Estimated Man-hours Consumed:
Estimated 250,200
Description:


Provision of Engineering, Procurement, Construction and Completion (EPC) of Early Civil Works Phase 2 for Petronas Carigali Iraq Holding B.V Garraf Operations.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
16,161,924
Type Of Work:
EPC Early Civil Works
Start Date:
September 2015
Completion Date:
July 2016
Estimated Man-hours Consumed:
372,716
Description:

This was an EPC Project for Early Civil Works for 9 different areas approx. 840,217 m2, road construction (3.5 Km) and drain works for 7 km approx. Other works included supply & installation of power lights, fence & gate for P&E laydown area and construction of guard house.



GENERAL CIVIL WORKS IRAQ WEST QURNA 1 - (M095) DS7 ISBL WATER INJECTION SYSTEM
PROJECT DESCRIPTION
Company(Client):
Saipem Iraq
ATCO Role:
Sub Contractor
Total Project Value (USD):
2,153,171
Type Of Work:
Civil
Start Date:
August 2013
Completion Date:
September 2015
Estimated Man-hours Consumed:
35,886
Description:

ATCO scope included the development of Water injection facilities , scope comprised earth works, excavation & backfilling, installation of piles, development of equipment foundations, steel structural works, installation of mechanical equipment, installation of piping & tubing, hydro testing, leak tests, laying of E & I cables, loop testing, installation of field instruments, commissioning of developed facilities.



EPCC for Expansion of Offsite 1 & Offsite 2 for Petronas Cargali Iraq Holding B.V Garraf Operations.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
18,682,698
Type Of Work:
EPCC. Civil, Piping, Mechanical and E&I works
Start Date:
January 2014
Completion Date:
August 2015
Estimated Man-hours Consumed:
1,200,000
Description:

ATCO scope included development works of 12 wellheads which comprised of area preparation, supply and pouring of 4000 m3 of concrete for pipe supports, mechanical equipments, E & I instruments and CCR foundations, Supply fabrication and installation of 80 tons of steel structure , fabrication and installation piping 12000 Dia inches for flow lines & interconnecting piping , Radiographic testing, hydro testing, surface preparation and painting for installed piping and steel structure, Laying, termination , dressing & connections , loop testing of E & I Cables, installation of control and F & G instruments, supply and installation of CCR, terminations and connections inside CCR, Piping and E & I Tie in connections of new facilities with existing facilities.



Provision of Engineering, Procurement ,Construction and Completion (EPC) Of Early Civil Works Phase 1 for Petronas Carigali Holding B.V. Garraf Operations.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
65,700,662
Type Of Work:
EPC Early Civil Works
Start Date:
13 Nov, 2013
Completion Date:
13 Sep , 2014
Estimated Man-hours Consumed:
2,300.000
Description:

ATCO Scope comprised of early civil works for development of 6 wellpads , power plant area, GSCC & several other area and 24.5Km of asphalt road. Early civil works included pouring of 33000m3 concrete, 38000 m3 of excavation and 1 million m3 of of soil back filling ,instalaltion of solar lighting system, supply & installation of T-Wall (approx. 7km) and earthing etc.



PROVISION of DESIGN, SUPPLY, INSTALLATION and COMMISSIONING of CONTAINERIZED REVERSE OSMOSIS SYSTEM for PETRONAS CARGALI IRAQ HOLDING B.V.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
947,000
Type Of Work:
pipe line, mechanical / piping , civil / biulding / steel structure, electrical.
Start Date:
26 May,2013
Completion Date:
1 Dec,2013
Estimated Man-hours Consumed:
11,838
Description:

ATCO scope included design, supply ,installation and commissioning of 3 units of containerized RO system, 60,000 liters/day capacity, FRP water storage tanks, 20,000 liters capacity ,& Related Civil foundations , interconnecting pipng and E & I Works.



PROVISION for SUPPLY and INSTALLATION of SECURITY CABINS and OPERATION and MAINTAINCE
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor
Total Project Value (USD):
665,000
Type Of Work:
Civil / building / steel structure.
Start Date:
4 Mar, 2013
Completion Date:
1 May,2013
Estimated Man-hours Consumed:
8,313
Description:

ATCO scope included Delivery and Installation of 7 nos.of 4m x 6m Prefabricated Cabin c/w Furniture, Toilet, Bed, Air Condition, Septic Tank, Water Tank Piping, Genset and Maintenance & Operation of the same facility for a period of 6 months.



ENGINEERING, PROCUREMENT, CONSTRUCTION and COMMISSIONING of MUNICIPAL WASTE WATER TREATMENT PLANT in BAIJI CITY.
PROJECT DESCRIPTION
Company(Client):
Saleh Adein Province Municipality
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
47,438,877
Type Of Work:
pipe line, mechanical / piping, civil / building / steel structure, electrical
Start Date:
15 Dec, 2011
Completion Date:
Closed
Estimated Man-hours Consumed:
368,969
Description:

• Approx. 15,000 engineering man hours and 144,450 site man hours
• EPCC of municipal waste water treatment plant
• Trench works, Laying of water pipes and related civil foundations
• Installation of waterpumps and related equipment



ENGINEERING , PROCUREMENT, CONSTRUCTION and COMMISSIONING of BASE CAMP with all FACILITIES.
PROJECT DESCRIPTION
Company(Client):
SPEC & ATCO
ATCO Role:
main contractor
Total Project Value (USD):
2,000,000
Type Of Work:
civil / building / steel structure
Start Date:
31 Mar , 2011
Completion Date:
5 May, 2011
Estimated Man-hours Consumed:
27,738
Description:

We provided specialized personnel and equipment requested to carry out work activities for supplying and installing mobile portable cabins for accommodation,offices, bathrooms and recreation areas. This camp contains of 55 mobile caravans that can accommodate about 100 persons. We have also built steel prefab workshop and diesel generators sets with sheds and accessories.



ENGINEERING , PROCUREMENT , CONSTRUCTION AND COMMISSIONING OF FCP (FIRST COMMERCIAL PRODUCTION) OFFSITE WELL CLUSTER 1.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
18,000,000
Type Of Work:
pipe line, mechanical / piping , civil / building / steel structure , electrical
Start Date:
January 2011
Completion Date:
July 2013
Estimated Man-hours Consumed:
1,013,238
Description:

APPROX. 45,000 ENGINEERING MAN HOURS AND 980,000 SITE MAN HOURS.

CONSTRUCTION AND PRE-COMMISSIONING OF API5L TRUNK LINE OF CRUDE OIL , 18”,  INCH FLOW LINE 8”.

CONSTRUCTION AND PRE-COMMISSIONING OF PIPE LINE OF HDPE FOR RIVER WATER HAVING DIAMETER 4” AND 2”.

CIVIL WORKS FOR EQUIPMENT FOUNDATIONS, DRAIN CHANNEL AND PIT.

EQUIPMENT INSTALLATION INCLUDING PIG LAUNCHER, PIG RECEIVER, DOSING PACKAGES, ELECTRICAL EQUIPMENT
CONSTRUCTION AND PRE-COMMISSIONING OF API5L TRUNK LINE OF CRUDE OIL , 18”,  INCH FLOW LINE 8”.



Rehabilitation and Renovation of Al-Hila Surgery Hospital
PROJECT DESCRIPTION
Company(Client):
Babel Province
ATCO Role:
JV with Al Khadra Co.
Total Project Value (USD):
7,500,000
Type Of Work:
Reconstruction & Renovation
Start Date:
December 2008
Completion Date:
Closed
Estimated Man-hours Consumed:
250,000
Description:

Rehabilitation and Renovation of Al-Hila Surgery Hospital



SUPPLYING & INSTALLATION of STEEL SECURITY NETS for MOSUL DAM PROJECT
PROJECT DESCRIPTION
Company(Client):
Ministry of Water Resources
ATCO Role:
Sub Contractor
Total Project Value (USD):
16,826,844
Type Of Work:
mechanical / building / steel structure
Start Date:
December 2008
Completion Date:
December 2010
Estimated Man-hours Consumed:
560,900
Description:

AL TAFAWEQ Company initiated mobilization / demobilization; we provided specialized personnel and equipment as requested by the client to carry out the job. Work includes supplying prefabricated steel buoys linked to nets consisted of steel wire ropes, cast in site huge anchor blocks to support the lines of the nets inside the lake of the dam, and install cathodic protection system.



PROVISION and INSTALLATION of HIGH VOLTAGE TRANSMISSION LINE 400 KV
PROJECT DESCRIPTION
Company(Client):
Ministry of Electricity
ATCO Role:
Sub Contractor
Total Project Value (USD):
3,275,000
Type Of Work:
Ministry of Electrity
Start Date:
23 Oct,2008
Completion Date:
5 Mar, 2009
Estimated Man-hours Consumed:
92,500
Description:

Provision and Installation of galvanized steel electrical towers 400 KV.
Work also included surveys, excavation, pouring concrete footings, installed the steel tower with all overhead aluminum Conductors.
We performed successfully as a prime Contractor for MOE Performing all the work specified on this project except design.



PROVISION & INSTALLATION of ELECTRICAL NETWORKS with TRANSFORMERS for LOW TENSION in FOUR DISCTRICTS
PROJECT DESCRIPTION
Company(Client):
general directorate for electricity
ATCO Role:
Sub Contractor
Total Project Value (USD):
1,308,588
Type Of Work:
electrical
Start Date:
11 Aug , 2007
Completion Date:
28 Oct , 2007
Estimated Man-hours Consumed:
19,292
Description:

We provided and installed overhead aluminum Conductors and transformers for low tension in four districts including provision and installation of 250 kv a. 400 kv a and 600 kva Transformers.
we performed successfully as a prime contractor for Al Anbar General Directorate for Electricity performing all of the work specified on the project except detailed design



PROVISION & INSTALL 2-WATER TREATMENT PLANT COMPACT UNITS INCLUDING PIPELINE NETWORKS
PROJECT DESCRIPTION
Company(Client):
General directorate for water supply
ATCO Role:
sub contractor
Total Project Value (USD):
1,716,876
Type Of Work:
Civil / Mechanical / Piping
Start Date:
18 Feb , 2007
Completion Date:
9 Aug , 2007
Estimated Man-hours Consumed:
65,300
Description:

Supplied and Installed two Water Treatment Plant Compact units for potable water with Capacity 200 m3/hr. Coordinated Sscurity in Mosul an extremely high Security area. Also installed steel structure for water intake along the river side and laid pipeline network consisting of DIP, CSP, UPVC pipe along with all associated Civil Works. We participated successfully as a prime contractor to the General Directorate for water supply, performing all of the work specified on this Project.



REHABILITATION of BAGHDAD POTABLE WATER DISTRIBUTION SYSTEM
PROJECT DESCRIPTION
Company(Client):
Parsons
ATCO Role:
Sub Contractor
Total Project Value (USD):
7,000,000
Type Of Work:
Civil/ mechanical / piping
Start Date:
3 Dec, 2004
Completion Date:
16 Nov, 2005
Estimated Man-hours Consumed:
461,240
Description:

ATCO Performed investigations and Surveys. Coordinated Security in Sadr City an extremely high Security area. Supplied and Installed the water distribution network including excavation. dewatering. shoring, compacting and leveling the natural earth. Also padding the ditch with a base Layer of sand, installing pipes and connections.  backfilling with sand soil and mixed aggregate sub base. Paved the road with 10 cm thick by using Concrete asphalt pavement. We participated successfully as a subcontractor to parsons and performed all of the work specified on this project except detailed design. See the attached Certificate of Appreciation from Parsons for our Successful Completion of this project while maintaining a high standards of quality, security and safety.



REHABILITATION of REBEA'A POINT of ENTRY and Construct Pump Station in MOSUL.
PROJECT DESCRIPTION
Company(Client):
Parsons
ATCO Role:
Sub Contractor
Total Project Value (USD):
798,704
Type Of Work:
Civil
Start Date:
09 Sep, 2004
Completion Date:
10 Aug, 2005
Estimated Man-hours Consumed:
72,200
Description:

ATCO scope included Supplying and Installation Prefabricated Caravans for administration and Accommodation to the employees of the Complex. Coordinated Security in Mosul.

Excavated the foundation performed excavated and poured Concrete footings. Cast in site ways, cast floors, roofs. Provided and installed prefabricated steel structure for searching shades, reinforced Concrete deck. Concrete asphalt pavement. Providing guard rails and lighting and provision and installation of two pumping sets with electrical boards and panels.

We worked as a sub-Contractor to Parsons and executed all the specified work in the Contract in addition to design.



DOWNLOAD ATCO PROFILE
Copyright © 2015 ATCO | All Rights Reserved. | Powered by Xotox Branding Agency
Al-Tafaweq Co. for General Contracts, ltd.