Provision of Engineering, Procurement, Construction and Commissioning (EPCC) of Garraf Central Control Building (GCCB) for Petronas Carigali Iraq Holding B.V.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq Holding B.V
ATCO Role:
Main Contractor
Total Project Value (USD):
10,587,432
Type Of Work:
Engineering, Procurement, Construction and Commissioning (EPCC)
Start Date:
August 2017
Completion Date:
March 2019
Estimated Man-hours Consumed:
630,000
Description:

Total Plot Plan Area= 14,000 sq. m, Total covered area for building=3,552 sq. m, Total Landscaping area=5,000 sq. m, Fence & Road around the building = 500m, Storm water drainage 300m, Covered Car parking 25 nos.
Honeywell DCS/SIS/FGS System (including 600 graphics, 165 I/O, 3 nos. Orion Consoles, 10 cabinets), ACS, PAGA, CCTV, VHF, Weather monitoring system and FOC.
Electrical works including Substation, Switchgear, Transformer 1.6KVA, EGD 425 KVA, UPS & Accessories.
Fire Detection & Alarm System, HVAC Package 150 tons.