ATCO scope included development works of 12 wellheads which comprised of area preparation, supply and pouring of 4000 m3 of concrete for pipe supports, mechanical equipments, E & I instruments and CCR foundations, Supply fabrication and installation of 80 tons of steel structure , fabrication and installation piping 12000 Dia inches for flow lines & interconnecting piping , Radiographic testing, hydro testing, surface preparation and painting for installed piping and steel structure, Laying, termination , dressing & connections , loop testing of E & I Cables, installation of control and F & G instruments, supply and installation of CCR, terminations and connections inside CCR, Piping and E & I Tie in connections of new facilities with existing facilities.