GENERAL CIVIL WORKS IRAQ WEST QURNA 1 - (M095) DS7 ISBL WATER INJECTION SYSTEM
PROJECT DESCRIPTION
Company(Client):
Saipem Iraq
ATCO Role:
Sub Contractor
Total Project Value (USD):
2,153,171
Type Of Work:
Civil
Start Date:
August 2013
Completion Date:
September 2015
Estimated Man-hours Consumed:
35,886
Description:

ATCO scope included the development of Water injection facilities , scope comprised earth works, excavation & backfilling, installation of piles, development of equipment foundations, steel structural works, installation of mechanical equipment, installation of piping & tubing, hydro testing, leak tests, laying of E & I cables, loop testing, installation of field instruments, commissioning of developed facilities.