Provision of Engineering, Procurement ,Construction and Completion (EPC) Of Early Civil Works Phase 1 for Petronas Carigali Holding B.V. Garraf Operations.
PROJECT DESCRIPTION
Company(Client):
Petronas Carigali Iraq B.V
ATCO Role:
Main Contractor (Consortium)
Total Project Value (USD):
65,700,662
Type Of Work:
EPC Early Civil Works
Start Date:
13 Nov, 2013
Completion Date:
13 Sep , 2014
Estimated Man-hours Consumed:
2,300.000
Description:

ATCO Scope comprised of early civil works for development of 6 wellpads , power plant area, GSCC & several other area and 24.5Km of asphalt road. Early civil works included pouring of 33000m3 concrete, 38000 m3 of excavation and 1 million m3 of of soil back filling ,instalaltion of solar lighting system, supply & installation of T-Wall (approx. 7km) and earthing etc.



DOWNLOAD ATCO PROFILE
Copyright © 2015 ATCO | All Rights Reserved. | Powered by Xotox Branding Agency
Al-Tafaweq Co. for General Contracts, ltd.